Solar + storage project J2821, Crittenden County

Solar + storage project J2821, Crittenden County is a 30.0 MW solar + storage request withdrawn in the MISO interconnection queue, in Crittenden County, Kentucky, connecting to BIG RIVERS ELECTRIC CORPORATION.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2821
Grid region
MISO (Midcontinent)
Utility / transmission owner
BIG RIVERS ELECTRIC CORPORATION
Connection point (POI)
Sullivan - Marion Jct 69 kV
Location
Crittenden County, Kentucky
Technology
Solar: 30.0 MW Β· Battery
Total requested
30.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
8 September 2022
Proposed online date
March 2025
Withdrawn
October 2025

Location

Marker shows the centre of Crittenden County; the queue data does not give exact sites.