United States β€Ί Grid β€Ί Interconnection queues β€Ί Kentucky

SOLAR + STORAGE Β· PJM

Solar + storage project AG2-179, Adair County

Solar + storage project AG2-179, Adair County is a 60.0 MW solar + storage request withdrawn in the PJM interconnection queue, in Adair County, Kentucky, connecting to EKPC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2025 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-179
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
EKPC
Developer
Round Trip, LLC
Connection point (POI)
Sewellton Junction 69 kV
Location
Adair County, Kentucky
Technology
Solar: 60.0 MW Β· Battery
Total requested
60.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
14 March 2025
Proposed online date
September 2023
Withdrawn
December 2025

Location

Marker shows the centre of Adair County; the queue data does not give exact sites.