United States βΊ Grid βΊ Interconnection queues βΊ Kentucky
SOLAR Β· PJMSolar project AC2-114, Campbell County
Solar project AC2-114, Campbell County is a 49.9 MW solar request withdrawn in the PJM interconnection queue, in Campbell County, Kentucky, connecting to EKPC.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2017 (completed)
- Withdrawn / abandonedSep 2017 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AC2-114
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- EKPC
- Connection point (POI)
- Magnolia-Summersville 69kV
- Location
- Campbell County, Kentucky
- Technology
- Solar: 49.9 MW
- Total requested
- 49.9 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 20 March 2017
- Proposed online date
- July 2019
- Withdrawn
- September 2017
Location
Marker shows the centre of Campbell County; the queue data does not give exact sites.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem