OCTARY USA · INTERCONNECTION QUEUES

Solar interconnection queue in the USA — page 53

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,995427.5 GW
Active in queue427.5 GW2,995 requests
Agreement signed108.2 GW781 requests
Withdrawn9,252860.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,995 requests · page 53 of 60
ProjectCapacityStatusLocationRegionQueuedOnline
Somers Solar, LLC
Solar · Somers Solar, LLC
20.0 MWIn study Washington, NYNYISO May 2020target 2026
Concho Solar I
Solar
20.0 MWPaused / redesign Queen Anne's, MDPJM May 2019target 2024
Solar project Q246, Yuma County
Solar
20.0 MWAgreement signed Yuma, AZWest Sep 2016target 2021
SunEast Skyline Solar LLC
Solar · SunEast Skyline Solar LLC
20.0 MWIn study Oneida, NYNYISO Sep 2017target 2028
Cedar Creek Solar
Solar
20.0 MWPaused / redesign Kent, DEPJM Apr 2017target 2027
SunEast Flat Stone Solar LLC
Solar · SED NY Holdings LLC
20.0 MWIn study Oneida, NYNYISO Mar 2020target 2026
Farmers Valley Solar
Solar
20.0 MWAgreement signed Bradford, PAPJM Mar 2020target 2028
Little Pond Solar
Solar · Little Pond Solar, LLC
20.0 MWIn study Orange, NYNYISO Sep 2016target 2027
Hills Solar
Solar · SunEast Hills Solar LLC
20.0 MWIn study Herkimer, NYNYISO Oct 2016target 2026
Mountain Holly
Solar
20.0 MWPaused / redesign Columbia, PAPJM Mar 2019target 2027
Hatchery Solar
Solar · Hatchery Solar LLC
20.0 MWIn study Livingston, NYNYISO Oct 2019target 2026
Solar project AH1-571
Solar · South Fork Solar, LLC
20.0 MWIn study KYPJM Mar 2025target 2024
Amelia Energy Facility
Solar · Amelia Energy Facility, LLC
20.0 MWIn study Amelia, VAPJM May 2020target 2023
Flat Hill Solar
Solar · Flat Hill Solar NY LLC.
20.0 MWIn study Herkimer, NYNYISO May 2019
Solar project G1069, Harney County
Solar
20.0 MWIn study Harney, ORWest Jul 2024target 2025
Solar project J3065, Oceana County
Solar
20.0 MWIn study Oceana, MIMISO Sep 2022target 2025
Dog Corners Solar
Solar · SunEast Dog Corners Solar LLC
20.0 MWIn study Cayuga, NYNYISO Nov 2016target 2026
Solar project AH2-160, Highland County
Solar
20.0 MWIn study Highland, OHPJM Mar 2022target 2025
Switchgrass Solar 1
Solar
20.0 MWPaused / redesign Accomack, VAPJM Feb 2020target 2025
Nutes Solar
Solar
20.0 MWAgreement signed Strafford, NHISO-NE May 2021target 2026
Eaton OH Solar
Solar
20.0 MWAgreement signed Preble, OHPJM Feb 2017target 2027
Franklin Solar
Solar
20.0 MWAgreement signed Crawford, PAPJM Aug 2019target 2026
Solar project AH2-063, Beaver County
Solar
20.0 MWIn study Beaver, PAPJM Dec 2021target 2023
FR-Williamsport
Solar
20.0 MWAgreement signed Franklin, PAPJM Sep 2019target 2025
Morris Solar
Solar · Morris Solar NY LLC
20.0 MWIn study St. Lawrence, NYNYISO Jan 2021target 2028
Rochelle Solar
Solar
20.0 MWAgreement signed Ogle, ILPJM Sep 2019target 2028
Frosty Valley Energy Center
Solar
20.0 MWAgreement signed Columbia, PAPJM Mar 2020target 2027
Walnut Solar I
Solar
20.0 MWAgreement signed King And Queen, VAPJM Mar 2017target 2026
Solar project GEN-2020-056, Russell County
Solar
20.0 MWAgreement signed Russell, KSSPP Apr 20202025
Cedar Creek Solar
Solar
20.0 MWPaused / redesign Kent, DEPJM Apr 2017target 2027
HU-Pauls
Solar
20.0 MWPaused / redesign Huntingdon, PAPJM Mar 2019target 2027
Club Ford Energy Center
Solar
20.0 MWAgreement signed Adams, PAPJM Apr 2020target 2028
Kincaid PV
Solar
20.0 MWAgreement signed Christian, ILPJM Oct 2019target 2028
CL-Green Acres
Solar
20.0 MWAgreement signed Clearfield, PAPJM Sep 2019target 2028
Montour 1
Solar
20.0 MWPaused / redesign Columbia, PAPJM Mar 2019target 2025
Limestone Solar
Solar
20.0 MWAgreement signed Union, PAPJM Sep 2019target 2027
Solar project AG2-193, Henrico County
Solar · Virginia Electric and Power Company
20.0 MWIn study Henrico, VAPJM Feb 2025target 2023
Clear View Solar
Solar · Clear View LLC
20.0 MWIn study Steuben, NYNYISO Apr 2020
Solar project G0516, Sherman County
Solar
20.0 MWIn study Sherman, ORWest Oct 2015target 2016
Blue Creek Wind Farm
Solar
20.0 MWPaused / redesign Van Wert, OHPJM Feb 2017target 2024
Solar project 815, Emery County
Solar · Pivot 13, LLC
20.0 MWAgreement signed Emery, UTWest Nov 2016target 2025
Cricket Solar
Solar
20.0 MWAgreement signed Culpeper, VAPJM Oct 2016target 2029
Limestone Solar
Solar
20.0 MWAgreement signed Union, PAPJM Sep 2019target 2027
Walnut Solar I
Solar
20.0 MWAgreement signed King And Queen, VAPJM Oct 2018target 2026
Chester Solar Technology Park
Solar
20.0 MWAgreement signed Chesterfield, VAPJM Sep 2019target 2027
WA-Cochecton 2
Solar
20.0 MWAgreement signed Adams, PAPJM Mar 2020target 2027
Solar project AI2-346, Harrison County
Solar
20.0 MWIn study Harrison, OHPJM Mar 2023target 2025
Jackson Center Solar Facility
Solar
20.0 MWAgreement signed Mercer, PAPJM Sep 2018target 2026
Ticonderoga Solar
Solar · ELP Ticonderoga Solar LLC
20.0 MWIn study Essex, NYNYISO Jun 2018target 2026
Solar project BHBE G22, Meade County
Solar
20.0 MWAgreement signed Meade, SDWest Oct 2022target 2024
Page 53 of 60

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)