SOLAR · PJMSolar project AG2-193, Henrico County
Solar project AG2-193, Henrico County is a 20.0 MW solar request in interconnection study in the PJM interconnection queue, in Henrico County, Virginia, connecting to Dominion.
Queue statusIn planning
- PlanningQueued Feb 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2023 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AG2-193
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Developer
- Virginia Electric and Power Company
- Connection point (POI)
- Turner 34.5 kV
- Location
- Henrico County, Virginia
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study
- Queue status
- Active
- Entered queue
- 20 February 2025
- Proposed online date
- December 2023
Location
Marker shows the centre of Henrico County; the queue data does not give exact sites.
Other requests in Henrico County
- Spruance Operating Services LLCGas · 66.0 MW · built
- Darbytown GT4Gas · 20.0 MW · built
- Darbytown GT1Gas · 20.0 MW · built
- Darbytown GT3Gas · 20.0 MW · built
- Darbytown GT2Gas · 20.0 MW · built
- Briel Farm SolarSolar · 18.8 MW · built
- Richmond Energy FacilityOther · 8.0 MW · built
- Henrico County LandfillOther · 4.0 MW · built
- Briel Farm SolarSolar · 1.3 MW · built
- Solar project AD2-056, Henrico CountySolar · 20.0 MW · withdrawn
- Turner I SolarSolar · 20.0 MW · withdrawn
- Other project R98, Henrico CountyOther · 14.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem