United States βΊ Grid βΊ Interconnection queues βΊ Virginia
SOLAR Β· PJMTurner I Solar
Turner I Solar is a 20.0 MW solar request withdrawn in the PJM interconnection queue, in Henrico County, Virginia, connecting to Dominion.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2017 (completed)
- Withdrawn / abandonedSep 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AD1-048
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Turner 34.5 kV
- Location
- Henrico County, Virginia
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
- Queue status
- Withdrawn
- Entered queue
- 3 August 2017
- Proposed online date
- December 2022
- Withdrawn
- September 2019
Location
Marker shows the centre of Henrico County; the queue data does not give exact sites.
Other requests in Henrico County
- Solar project AG2-193, Henrico CountySolar Β· 20.0 MW Β· in study
- Spruance Operating Services LLCGas Β· 66.0 MW Β· built
- Darbytown GT4Gas Β· 20.0 MW Β· built
- Darbytown GT1Gas Β· 20.0 MW Β· built
- Darbytown GT3Gas Β· 20.0 MW Β· built
- Darbytown GT2Gas Β· 20.0 MW Β· built
- Briel Farm SolarSolar Β· 18.8 MW Β· built
- Richmond Energy FacilityOther Β· 8.0 MW Β· built
- Henrico County LandfillOther Β· 4.0 MW Β· built
- Briel Farm SolarSolar Β· 1.3 MW Β· built
- Solar project AD2-056, Henrico CountySolar Β· 20.0 MW Β· withdrawn
- Other project R98, Henrico CountyOther Β· 14.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem