Clear View Solar

Clear View Solar is a 20.0 MW solar request in interconnection study in the NYISO interconnection queue, in Steuben County, New York, connecting to NYSEG.

Queue statusIn planning
  1. PlanningQueued Apr 2020 (current stage)
  2. ConsentedSep 2022 (not yet reached)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
1003
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
Clear View LLC
Connection point (POI)
Eelpot Road 34.5 kV
Location
Steuben County, New York
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Study phase
SIS, FS
Queue status
Active
Entered queue
6 April 2020
Agreement signed
6 September 2022

Location

Marker shows the centre of Steuben County; the queue data does not give exact sites.