🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in the USA (2020 requests) — page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown29757.2 GW
Active in queue117.0 GW635 requests
Agreement signed57.7 GW326 requests
Withdrawn1,752246.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

297 requests · page 5 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J1714, Fayette County
Solar
100 MWIn study Fayette, ILMISO Jun 2020target 2026
Battery storage project J1844, Washtenaw County
Battery storage
100 MWIn study Washtenaw, MIMISO Dec 2020target 2024
Solar project J1736, Dubois County
Solar
100 MWIn study Dubois, INMISO Jun 2020target 2023
RV Solar
Solar
100 MWIn study Tattnall, GASoutheast Feb 20202022
Battery storage project Q363, Maricopa County
Battery storage
100 MWIn study Maricopa, AZWest Sep 2020target 2023
Grand Marsh Solar
Solar · Deriva Energy Solar, LLC
100 MWIn study Kankakee, ILPJM Mar 2020target 2023
Solar project J1795, Acadia Parish County
Solar
100 MWIn study Acadia Parish, LAMISO Jun 2020target 2025
Red Maple Solar
Solar · Red Maple Solar, LLC
95.1 MWIn study Dekalb, ILPJM Aug 2020target 2023
Solar + storage project IA-PNM-2020-06, Mckinley County
Solar + storage
90.0 MWIn study Mckinley, NMWest May 2020target 2023
Wild Rose Solar Project
Solar · Wild Rose Solar Project, LLC
90.0 MWIn study Nelson, VAPJM Aug 2020target 2024
Ambrosia Solar
Solar + storage · Ambrosia Solar
90.0 MWPaused / redesign Mckinley, NMWest Oct 2020target 2023
Wildcat Solar Power Plant
Solar + storage
90.0 MWPaused / redesign Mckinley, NMWest Oct 2020target 2023
Gas project 415, Manatee County
Gas · FPL
87.0 MWIn study Manatee, FLSoutheast Sep 2020target 2026
Solar + storage project IC-925, Houston County
Solar + storage
80.0 MWPaused / redesign Houston, ALSoutheast Dec 2020target 2027
Other project GI-2020-139, Riverside County
Other
80.0 MWIn study Riverside, CAWest Nov 2020target 2027
Other project 72, Pima County
Other
80.0 MWIn study Pima, AZWest Jan 2020target 2022
Solar project IC-926, Montgomery County
Solar
80.0 MWPaused / redesign Montgomery, ALSoutheast Dec 2020target 2027
Kce NY 29
Battery storage · KCE NY 29, LLC
79.0 MWIn study Suffolk, NYNYISO Dec 2020target 2027
Gas project 417, Volusia County
Gas · FPL
76.0 MWIn study Volusia, FLSoutheast Sep 2020target 2025
Brunswick Battery Storage
Battery storage · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
75.0 MWIn study Brunswick, VAPJM Sep 2020target 2031
Noria Storage
Battery storage
75.0 MWPaused / redesign Nueces, TXERCOT Aug 2020target 2025
Solar project BHCT G28, Pueblo County
Solar
75.0 MWIn study Pueblo, COWest Feb 2020target 2023
Solar project 290, Suwannee County
Solar · Echo River Solar Project, LLC
74.9 MWIn study Suwannee, FLSoutheast Dec 2020target 2025
Solar project 408, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Jul 2020target 2026
Solar project 411, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Jul 2020target 2028
Solar project 413, Desoto County
Solar · FPL
74.5 MWIn study Desoto, FLSoutheast Jul 2020target 2027
Solar project 283, Gilchrist County
Solar · Florida Renewable Partners, LLC
74.5 MWPaused / redesign Gilchrist, FLSoutheast Apr 2020target 2022
Solar project 405, Okeechobee County
Solar · FPL
74.5 MWIn study Okeechobee, FLSoutheast Jul 2020target 2027
Solar project 412, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Jul 2020target 2028
Solar project 406, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Jul 2020target 2027
Solar project 286, Gilchrist County
Solar · FRP Gadsden County Solar, LLC
74.5 MWIn study Gilchrist, FLSoutheast Jun 2020target 2023
Solar project 398, Putnam County
Solar · FPL
74.5 MWIn study Putnam, FLSoutheast Jul 2020target 2032
Solar project 407, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Jul 2020target 2027
Solar project 378H, Walton County
Solar · FPL
74.5 MWIn study Walton, FLSoutheast Feb 2020target 2027
Solar project 410, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Jul 2020target 2028
Solar project 414, Desoto County
Solar · FPL
74.5 MWIn study Desoto, FLSoutheast Jul 2020target 2029
Harmony 2
Solar
74.5 MWIn study Osceola, FLSoutheast Dec 2020target 2024
Solar project 404, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Jul 2020target 2026
Solar project 284, Alachua County
Solar · Florida Renewable Partners, LLC
74.5 MWIn study Alachua, FLSoutheast Apr 2020target 2022
Onshore wind project J1575, Marshall County
Onshore wind
70.0 MWIn study Marshall, MNMISO Jun 2020target 2028
Clies 70MW
Battery storage · Caithness LI Energy Storage, LLC
70.0 MWIn study Suffolk, NYNYISO Nov 2020target 2027
Creekfield Storage
Battery storage
69.0 MWPaused / redesign Fort Bend, TXERCOT Nov 2020
Cerulean Solar and Mulberry BESS
Solar · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
62.0 MWIn study Richmond, VAPJM Feb 2020target 2031
Celeste Energy Storage
Battery storage
60.9 MWPaused / redesign Pecos, TXERCOT Apr 2020
Moon Corner Solar
Solar · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
60.0 MWIn study Richmond, VAPJM Sep 2020target 2031
Gas project 419, Martin County
Gas · FPL
60.0 MWIn study Martin, FLSoutheast Sep 2020target 2026
Battery storage project 376, Yellowstone County
Battery storage
58.8 MWPaused / redesign Yellowstone, MTWest May 2020target 2023
Bluestem Solar
Battery storage · RWE Solar Development, LLC
55.0 MWIn study Laporte, INPJM Sep 2020target 2023
Solar + storage project Q339, Yavapai County
Solar + storage
53.0 MWPaused / redesign Yavapai, AZWest Mar 2020target 2022
Onshore wind project GEN-2020-069, Cherry County
Onshore wind
52.9 MWIn study Cherry, NESPP Apr 20202025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)