🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Florida

SOLAR · SOUTHEAST

Solar project 286, Gilchrist County

Solar project 286, Gilchrist County is a 74.5 MW solar request in interconnection study in the Southeast interconnection queue, in Gilchrist County, Florida, connecting to Duke Energy Florida.

Queue statusIn planning
  1. PlanningQueued Jun 2020 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2023 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
286
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Florida
Developer
FRP Gadsden County Solar, LLC
Connection point (POI)
Hayfield Substation
Location
Gilchrist County, Florida
Technology
Solar: 74.5 MW
Total requested
74.5 MW
Service type
NRIS and ERIS
Study phase
Facility Study
Queue status
Active
Entered queue
2 June 2020
Proposed online date
December 2023

Location

Marker shows the centre of Gilchrist County; the queue data does not give exact sites.

Power plants in Florida · Transmission lines in Florida

Other requests in Gilchrist County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem