SOLAR · SOUTHEAST

Solar project 295, Gilchrist County

Solar project 295, Gilchrist County is a 74.9 MW solar request built and operating in the Southeast interconnection queue, in Gilchrist County, Florida, connecting to Duke Energy Florida.

Queue statusOperating
  1. PlanningQueued Sep 2021 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingAug 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
295
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Florida
Developer
Duke Energy Florida, LLC
Connection point (POI)
Ginnie 69 kV Substation
Location
Gilchrist County, Florida
Technology
Solar: 74.9 MW
Total requested
74.9 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Operational
Entered queue
9 September 2021
Proposed online date
August 2024
Came online
August 2024

Location

Marker shows the centre of Gilchrist County; the queue data does not give exact sites.