United States β€Ί Grid β€Ί Interconnection queues β€Ί Florida

GAS Β· SOUTHEAST

Gas project 90, Gilchrist County

Gas project 90, Gilchrist County is a 868 MW gas request withdrawn in the Southeast interconnection queue, in Gilchrist County, Florida, connecting to Duke Energy Florida.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2008 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
90
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Florida
Developer
Masked
Connection point (POI)
Gilchrist Substation
Location
Gilchrist County, Florida
Technology
Gas: 868 MW
Total requested
868 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
15 July 2008
Proposed online date
June 2014

Location

Marker shows the centre of Gilchrist County; the queue data does not give exact sites.

Power plants in Florida Β· Transmission lines in Florida

Other requests in Gilchrist County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem