United States βΊ Grid βΊ Interconnection queues βΊ Florida
GAS Β· SOUTHEASTGas project 88, Gilchrist County
Gas project 88, Gilchrist County is a 546 MW gas request withdrawn in the Southeast interconnection queue, in Gilchrist County, Florida, connecting to Duke Energy Florida.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2008 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 88
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Duke Energy Florida
- Developer
- Masked
- Connection point (POI)
- Gilchrist Substation
- Location
- Gilchrist County, Florida
- Technology
- Gas: 546 MW
- Total requested
- 546 MW
- Service type
- Network resource (NRIS)
- Queue status
- Withdrawn
- Entered queue
- 6 April 2008
- Proposed online date
- June 2013
Location
Marker shows the centre of Gilchrist County; the queue data does not give exact sites.
Other requests in Gilchrist County
- Solar project 171, Gilchrist CountySolar Β· 74.5 MW Β· in study
- Solar project 286, Gilchrist CountySolar Β· 74.5 MW Β· in study
- Solar project 283, Gilchrist CountySolar Β· 74.5 MW Β· suspended
- Solar project 324, Gilchrist CountySolar Β· 74.5 MW Β· suspended
- Solar project 336, Gilchrist CountySolar Β· 61.2 MW Β· suspended
- Solar project 160, Gilchrist CountySolar Β· 74.9 MW Β· built
- Solar project 295, Gilchrist CountySolar Β· 74.9 MW Β· built
- Solar project 174, Gilchrist CountySolar Β· 74.5 MW Β· built
- Solar project 154, Gilchrist CountySolar Β· 74.5 MW Β· built
- Gas project 90, Gilchrist CountyGas Β· 868 MW Β· withdrawn
- Solar project 262, Gilchrist CountySolar Β· 74.9 MW Β· withdrawn
- Solar project 218C, Gilchrist CountySolar Β· 74.9 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem