United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 49

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 49 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Horsethief Pumped Storage
Battery storage
500 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Solar project 412, Lawrence County
Solar
500 MWWithdrawn / abandoned Lawrence, ALSoutheast Jan 2020
Other project Q533, Coconino County
Other
500 MWWithdrawn / abandoned Coconino, AZWest Apr 2023target 2027
Coal project 20, Rosebud County
Coal
500 MWWithdrawn / abandoned Rosebud, MTWest Mar 2002target 2013
Lucerne Valley Solar Project, Phase 2
Solar
500 MWWithdrawn / abandoned San Bernardino, CACAISO Feb 2008target 2016
Hereford Wind
Onshore wind · Higher Power Energy, LLC
500 MWWithdrawn / abandoned ERCOT May 2011target 2050
Gas project 957043, Cherokee County
Gas
500 MWWithdrawn / abandoned Cherokee, SCSoutheast Jun 2024
Braen Energy Storage Project
Battery storage · Braen Energy LLC
500 MWWithdrawn / abandoned Rockland, NYNYISO Aug 2023
Pleasant Ridge Wind Farm
Onshore wind
500 MWWithdrawn / abandoned Livingston, ILPJM Oct 2006target 2020
Solar project 651, Lowndes County
Solar
500 MWWithdrawn / abandoned Lowndes, MSSoutheast Sep 2024
Braen Energy Storage Phase 1
Battery storage · Braen Energy LLC
500 MWWithdrawn / abandoned Rockland, NYNYISO Aug 2024
Solar project 560, Elmore County
Solar
500 MWWithdrawn / abandoned Elmore, IDWest Jun 2019
Mojave Soleil II
Solar
500 MWWithdrawn / abandoned Kern, CACAISO May 2008target 2011
Solar project J3427, Mississippi County
Solar
500 MWWithdrawn / abandoned Mississippi, ARMISO Mar 2024target 2028
Solar + storage project Company MF, Humboldt County
Solar + storage
500 MWWithdrawn / abandoned Humboldt, NVWest Sep 2021target 2024
Battery storage project Company PJ, Humboldt County
Battery storage
500 MWWithdrawn / abandoned Humboldt, NVWest Mar 2022target 2029
Gas project 567758, Davidson County
Gas
500 MWWithdrawn / abandoned Davidson, NCSoutheast Jun 2022
Gas project IC-003, Lowndes County
Gas
500 MWWithdrawn / abandoned Lowndes, MSSoutheast
Battery storage project Company PV, Eureka County
Battery storage
500 MWWithdrawn / abandoned Eureka, NVWest Mar 2023target 2028
Onshore wind project J192, Washington County
Onshore wind
500 MWWithdrawn / abandoned Washington, IAMISO Jan 2011target 2012
Battery storage project AG2-475, Charles City County
Battery storage
500 MWWithdrawn / abandoned Charles City, VAPJM Mar 2021target 2024
Gas project G06_W47, Allegheny County
Gas
500 MWWithdrawn / abandoned Allegheny, PAPJM Feb 2001target 2005
Island Gen. Station #2
Other · Fortistar Power Marketing, LLC
500 MWWithdrawn / abandoned NYNYISO Sep 2000
Other project IP11, Washington County
Other
500 MWWithdrawn / abandoned Washington, ILMISO Jul 2000target 2006
Other project 107, Desoto County
Other
500 MWWithdrawn / abandoned Desoto, MSSoutheast Jun 2000
Onshore wind project C3-016, Sweetwater County
Onshore wind
500 MWWithdrawn / abandoned Sweetwater, WYWest Apr 2023target 2025
Onshore wind project 191, Carbon County
Onshore wind
500 MWWithdrawn / abandoned Carbon, WYWest Jan 2008
Solar project J3441, Houston County
Solar
500 MWWithdrawn / abandoned Houston, TXMISO Mar 2024target 2028
Other project 16, Marshall County
Other
500 MWWithdrawn / abandoned Marshall, KYSoutheast Jul 1998
Solar + storage project 114, Pima County
Solar + storage
500 MWWithdrawn / abandoned Pima, AZWest Feb 2022target 2026
Ramapo Storage Project 1
Battery storage · Ramapo Storage Project 1
500 MWWithdrawn / abandoned Rockland, NYNYISO Jan 2023
Solar project GEN-2021-074, Prowers County
Solar
500 MWWithdrawn / abandoned Prowers, COSPP May 2021target 2026
Solar project J3937, Dallas County
Solar
500 MWWithdrawn / abandoned Dallas, ARMISO Apr 2025target 2030
Other project G159, Buchanan County
Other
500 MWWithdrawn / abandoned Buchanan, IAMISO Nov 2001target 2003
Onshore wind project GEN-2008-048, Kiowa County
Onshore wind
500 MWWithdrawn / abandoned Kiowa, COSPP May 2008target 2011
Battery storage project C3-152, Sevier County
Battery storage
500 MWWithdrawn / abandoned Sevier, UTWest May 2023target 2027
Battery storage project C2-21, Juab County
Battery storage · PacifiCorp
500 MWWithdrawn / abandoned Juab, UTWest Apr 2022target 2028
Solar + storage project Company ON, Esmeralda County
Solar + storage
500 MWWithdrawn / abandoned Esmeralda, NVWest Jan 2023target 2028
500MW Snohomish
Gas · FPL Energy Power Marketing Inc
500 MWWithdrawn / abandoned Snohomish, WAWest Jan 2001target 2002
Delta Wind II
Onshore wind
500 MWWithdrawn / abandoned Solano, CACAISO Feb 2007target 2011
Onshore wind project J2591, Choctaw County
Onshore wind
500 MWWithdrawn / abandoned Choctaw, MSMISO Sep 2022target 2028
Antelope Energy Storage Center
Battery storage · Antelope Energy Storage LLC
500 MWWithdrawn / abandoned Lewis, NYNYISO Sep 2024
Hydro project AE2-135, Schuylkill County
Hydro
500 MWWithdrawn / abandoned Schuylkill, PAPJM Mar 2019target 2022
Battery storage project Q04, Maricopa County
Battery storage
500 MWWithdrawn / abandoned Maricopa, AZWest Mar 2023target 2028
SV Energy Storage Facility
Battery storage
500 MWWithdrawn / abandoned San Diego, CACAISO Apr 2019target 2026
Onshore wind project G0633, Gilliam County
Onshore wind
500 MWWithdrawn / abandoned Gilliam, ORWest Dec 2019target 2023
Solar + storage project AE1-215, White County
Solar + storage
500 MWWithdrawn / abandoned White, INPJM Sep 2018target 2023
Solar + storage project C4-028, Blaine County
Solar + storage
500 MWWithdrawn / abandoned Blaine, IDWest May 2024target 2028
Onshore wind project Q62, Coconino County
Onshore wind
500 MWWithdrawn / abandoned Coconino, AZWest Feb 2009target 2015
Onshore wind project GI-2017-26, Bent County
Onshore wind
500 MWWithdrawn / abandoned Bent, COWest Aug 2017target 2020
Page 49 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)