United States βΊ Grid βΊ Interconnection queues βΊ Nevada
BATTERY STORAGE Β· WESTBattery storage project Company PV, Eureka County
Battery storage project Company PV, Eureka County is a 500 MW battery storage request withdrawn in the West interconnection queue, in Eureka County, Nevada, connecting to NV Energy.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2023 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- Company PV
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- NV Energy
- Location
- Eureka County, Nevada
- Technology
- Other Storage: 500 MW
- Total requested
- 500 MW
- Service type
- Network resource (NRIS)
- Queue status
- Withdrawn
- Entered queue
- 28 March 2023
- Proposed online date
- December 2028
Location
Marker shows the centre of Eureka County; the queue data does not give exact sites.
Other requests in Eureka County
- Geothermal project Company KG, Eureka CountyGeothermal Β· 38.5 MW Β· agreement signed
- Solar + storage project Company PO, Eureka CountySolar + storage Β· 140 MW Β· in study
- Solar + storage project Company NS, Eureka CountySolar + storage Β· 300 MW Β· suspended
- Solar + storage project Company LZ, Eureka CountySolar + storage Β· 200 MW Β· suspended
- Solar + storage project Company LY, Eureka CountySolar + storage Β· 200 MW Β· suspended
- Solar + storage project Company KK, Eureka CountySolar + storage Β· 100 MW Β· built
- Solar project Company KL, Eureka CountySolar Β· 100 MW Β· built
- Solar + storage project Company PP, Eureka CountySolar + storage Β· 350 MW Β· withdrawn
- Solar + storage project Company JU, Eureka CountySolar + storage Β· 300 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem