Solar + storage project Company PP, Eureka County

Solar + storage project Company PP, Eureka County is a 350 MW solar + storage request withdrawn in the West interconnection queue, in Eureka County, Nevada, connecting to NV Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Company PP
Grid region
West (non-ISO utilities)
Utility / transmission owner
NV Energy
Location
Eureka County, Nevada
Technology
Solar: 350 MW Β· Battery
Total requested
350 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
27 March 2023
Proposed online date
September 2025

Location

Marker shows the centre of Eureka County; the queue data does not give exact sites.

Power plants in Nevada Β· Transmission lines in Nevada

Other requests in Eureka County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem