Braen Energy Storage Project

Braen Energy Storage Project is a 500 MW battery storage request withdrawn in the NYISO interconnection queue, in Rockland County, New York, connecting to ConEd.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2023 (completed)
  2. Withdrawn / abandonedOct 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1599
Grid region
NYISO (New York)
Utility / transmission owner
ConEd
Developer
Braen Energy LLC
Connection point (POI)
Con Edison Ramapo Substation
Location
Rockland County, New York
Technology
Battery: 500 MW
Total requested
500 MW
Queue status
Withdrawn
Entered queue
31 August 2023
Withdrawn
October 2023

Location

Marker shows the centre of Rockland County; the queue data does not give exact sites.