United States β€Ί Grid β€Ί Interconnection queues β€Ί California

ONSHORE WIND Β· CAISO

Delta Wind II

Delta Wind II is a 500 MW onshore wind request withdrawn in the CAISO interconnection queue, in Solano County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2007 (completed)
  2. Withdrawn / abandonedApr 2011 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
171
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Vaca-Tesla 500kV line
Location
Solano County, California
Technology
Wind: 500 MW
Total requested
500 MW
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
9 February 2007
Proposed online date
March 2011
Withdrawn
April 2011

Location

Marker shows the centre of Solano County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Solano County