United States βΊ Grid βΊ Interconnection queues βΊ Washington
GAS Β· WEST500MW Snohomish
500MW Snohomish is a 500 MW gas request withdrawn in the West interconnection queue, in Snohomish County, Washington, connecting to FPL Energy Power Marketing Inc.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2001 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G19
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- FPL Energy Power Marketing Inc
- Developer
- FPL Energy Power Marketing Inc
- Connection point (POI)
- At 115 kV and 230 kV Snohomish Substation
- Location
- Snohomish County, Washington
- Technology
- Gas: 500 MW
- Total requested
- 500 MW
- Service type
- Energy only (ERIS)
- Queue status
- Withdrawn
- Entered queue
- 18 January 2001
- Proposed online date
- September 2002
Location
Marker shows the centre of Snohomish County; the queue data does not give exact sites.
Power plants in Washington Β· Transmission lines in Washington
Other requests in Snohomish County
- Battery storage project G0832, Snohomish CountyBattery storage Β· 25.0 MW Β· in study
- Solar project G0943, Snohomish CountySolar Β· 1.0 MW Β· in study
- YoungβΓΓ΄s Creek Hydro ProjectHydro Β· 8.0 MW Β· built
- Qualco ProjectOther Β· 3.0 MW Β· built
- MESA 2 Energy Storage ProjectBattery storage Β· 3.0 MW Β· built
- Battery storage project G0481, Snohomish CountyBattery storage Β· 2.0 MW Β· built
- Arlington MicrogridSolar + storage Β· 1.0 MW Β· built
- Hardeson Battery Storage ExpansionBattery storage Β· 1.0 MW Β· built
- Hardeson Battery StorageBattery storage Β· 1.0 MW Β· built
- Gas project 36, Snohomish CountyGas Β· 323 MW Β· withdrawn
- Gas project 22, Snohomish CountyGas Β· 302 MW Β· withdrawn
- 250MW SnohomishGas Β· 250 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem