Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 366 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project G0837, Morrow County
Gas
24.3 MWWithdrawn / abandoned Morrow, ORWest Feb 2023target 2023
Apparent First Hybrid
Solar + storage
24.1 MWWithdrawn / abandoned Yolo, CACAISO Oct 2010target 2022
Stony Brook Storage
Battery storage · Calpine Mid Atlantic Development, LLC
24.0 MWWithdrawn / abandoned Suffolk, NYNYISO Aug 2018
Brookfield substation - NG Western MA Area Cluster Study
Solar
24.0 MWWithdrawn / abandoned Worcester, MAISO-NE Mar 2019target 2020
Other project IC-258, Jefferson County
Other
24.0 MWWithdrawn / abandoned Jefferson, GASoutheast Sep 2011
Battery storage project 717, Owyhee County
Battery storage
24.0 MWWithdrawn / abandoned Owyhee, IDWest May 2023
Solar project IC-660, Richmond County
Solar
24.0 MWWithdrawn / abandoned Richmond, GASoutheast Dec 2017
Battery storage project J1429, Juneau County
Battery storage
24.0 MWWithdrawn / abandoned Juneau, WIMISO Apr 2019target 2022
Battery storage project AI1-093, Westmoreland County
Battery storage
24.0 MWWithdrawn / abandoned Westmoreland, PAPJM Aug 2022target 2026
Solar + storage project IA-PNM-2019-23, Luna County
Solar + storage
24.0 MWWithdrawn / abandoned Luna, NMWest Apr 2019target 2021
Solar project BHCT G34, Fremont County
Solar
24.0 MWWithdrawn / abandoned Fremont, COWest Jul 2022target 2025
Battery storage project AI1-094, Westmoreland County
Battery storage
24.0 MWWithdrawn / abandoned Westmoreland, PAPJM Aug 2022target 2026
Solar project AF2-357, Washington County
Solar
24.0 MWWithdrawn / abandoned Washington, MDPJM Mar 2020target 2023
Solar project GEN-2019-075, Johnson County
Solar
24.0 MWWithdrawn / abandoned Johnson, NESPP May 2019target 2027
Generator reactivation
Other
24.0 MWWithdrawn / abandoned Penobscot, MEISO-NE Apr 2019target 2020
Gas project E04, Monmouth County
Gas
24.0 MWWithdrawn / abandoned Monmouth, NJPJM Sep 2000
Solar project AH1-529, Bourbon County
Solar
24.0 MWWithdrawn / abandoned Bourbon, KYPJM Sep 2021target 2025
Onshore wind project G688, Murray County
Onshore wind
24.0 MWWithdrawn / abandoned Murray, MNMISO Oct 2006target 2008
Comanche Ridge Wind
Onshore wind · Baryonyx
24.0 MWWithdrawn / abandoned ERCOT Sep 2011target 2014
Onshore wind project 124, Cascade County
Onshore wind
24.0 MWWithdrawn / abandoned Cascade, MTWest Sep 2010target 2011
Riverhead Solar
Solar · Riverhead Solar Farm, LLC
24.0 MWWithdrawn / abandoned Suffolk, NYNYISO Jun 2014
Coal project G942, Lorain County
Coal
24.0 MWWithdrawn / abandoned Lorain, OHMISO Dec 2007target 2011
Bethpage Large Battery Energy Storage Project
Battery storage · Calpine Mid-Atlantic Development, LLC
24.0 MWWithdrawn / abandoned Nassau, NYNYISO Jun 2021
Other project G227, Ingham County
Other
24.0 MWWithdrawn / abandoned Ingham, MIMISO Apr 2002target 2002
Richardson Solar
Solar · AES DE DEVCO NC LLC
24.0 MWWithdrawn / abandoned St. Lawrence, NYNYISO Aug 2020
Mickleton Battery Storage
Battery storage
24.0 MWWithdrawn / abandoned Gloucester, NJPJM Nov 2019target 2028
Other project AD1-086
Other
23.9 MWWithdrawn / abandoned PJM Sep 2017target 2021
SNEW Summer '04 Temporary Generator
Other
23.8 MWWithdrawn / abandoned Fairfield, CTISO-NE Oct 2003target 2004
Gas Turbine Upgrade
Other
23.5 MWWithdrawn / abandoned New Haven, CTISO-NE Apr 2016target 2020
Solar + storage project C3-075, Lake County
Solar + storage
23.5 MWWithdrawn / abandoned Lake, ORWest May 2023target 2027
Solar project GEN-2021-SR3, Oklahoma County
Solar
23.4 MWWithdrawn / abandoned Oklahoma, OKSPP Feb 20212022
Battery storage project 186310, Durham County
Battery storage · Duke Energy Progress, LLC
23.3 MWWithdrawn / abandoned Durham, NCSoutheast Jul 2021
Other project G653d, Buchanan County
Other
23.3 MWWithdrawn / abandoned Buchanan, IAMISO Jul 2006target 2008
Onshore wind project J045, Pipestone County
Onshore wind
23.1 MWWithdrawn / abandoned Pipestone, MNMISO May 2009target 2010
Bishop
Onshore wind · Atlantic Renewable Energy Corp.
23.1 MWWithdrawn / abandoned Livingston, NYNYISO Sep 2003
Medeiros BESS
Battery storage
23.0 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Solar project AH1-045, Lake County
Solar · Zion Energy LLC
23.0 MWWithdrawn / abandoned Lake, ILPJM Jul 2021target 2023
Coal project J010, Oakland County
Coal
23.0 MWWithdrawn / abandoned Oakland, MIMISO Jan 2009target 2010
Gas turbine repowering (Alt. to Q647)
Gas
23.0 MWWithdrawn / abandoned Middlesex, CTISO-NE Jun 2019target 2025
Hovey Energy Storage
Battery storage · Barilla Solar, LLC
23.0 MWWithdrawn / abandoned ERCOT Jul 2023target 2026
Solar project IC-570, Pike County
Solar
23.0 MWWithdrawn / abandoned Pike, ALSoutheast Dec 2016
Solar + storage project 536, Malheur County
Solar + storage
23.0 MWWithdrawn / abandoned Malheur, ORWest Jun 2018
Onshore wind project GI-1307, Valley County
Onshore wind
23.0 MWWithdrawn / abandoned Valley, MTWest Jun 2013target 2013
Helm 1
Solar
23.0 MWWithdrawn / abandoned Fresno, CACAISO Nov 2011target 2015
Luna Mar
Battery storage
23.0 MWWithdrawn / abandoned San Mateo, CACAISO May 2017target 2021
Gas turbine repowering
Gas
23.0 MWWithdrawn / abandoned Middlesex, CTISO-NE Apr 2017target 2022
Oak Solar
Solar · Oak Lessee, LLC, d/b/a Oak Solar, LLC
23.0 MWWithdrawn / abandoned Northampton, NCPJM Aug 2020target 2024
Atwell West BESS Addition
Solar + storage
23.0 MWWithdrawn / abandoned Tulare, CACAISO Apr 2015target 2019
Coal project 202, Sweetwater County
Coal
23.0 MWWithdrawn / abandoned Sweetwater, WYWest Feb 2008target 2008
PV-03 Expansion
Solar
23.0 MWWithdrawn / abandoned Los Angeles, CACAISO Feb 2010target 2013
Page 366 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)