United States › Grid › Interconnection queues › Connecticut

OTHER · ISO-NE

Gas Turbine Upgrade

Gas Turbine Upgrade is a 23.5 MW other request withdrawn in the ISO-NE interconnection queue, in New Haven County, Connecticut.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2016 (completed)
  2. Withdrawn / abandonedJun 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
609
Grid region
ISO-NE (New England)
Connection point (POI)
POI is the CL&P Devon 115kv Substation
Location
New Haven County, Connecticut
Technology
Oil: 23.5 MW
Total requested
23.5 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
22 April 2016
Proposed online date
May 2020
Withdrawn
June 2016

Location

No county location in the queue data.

Power plants in Connecticut · Transmission lines in Connecticut

Other requests in New Haven County