SOLAR Β· SOUTHEAST

Solar project IC-660, Richmond County

Solar project IC-660, Richmond County is a 24.0 MW solar request withdrawn in the Southeast interconnection queue, in Richmond County, Georgia, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2017 (completed)
  2. Withdrawn / abandonedSep 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-660
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Dum Jon - Fort Gordon #2 115 kV Line
Location
Richmond County, Georgia
Technology
Solar: 24.0 MW
Total requested
24.0 MW
Service type
Energy only (ERIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
14 December 2017
Withdrawn
September 2018

Location

Marker shows the centre of Richmond County; the queue data does not give exact sites.

Power plants in Georgia Β· Transmission lines in Georgia

Other requests in Richmond County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem