SOLAR + STORAGE · CAISOApparent First Hybrid
Apparent First Hybrid is a 24.1 MW solar + storage request withdrawn in the CAISO interconnection queue, in Yolo County, California, connecting to PGAE.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2010 (completed)
- Withdrawn / abandonedApr 2025 (project stopped here)
- ConsentedMar 2014 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 653F
- Grid region
- CAISO (California)
- Utility / transmission owner
- PGAE
- Connection point (POI)
- Woodland-Davis 115 kV Line
- Location
- Yolo County, California
- Technology
- Solar: 12.0 MW · Battery: 12.1 MW
- Total requested
- 24.1 MW
- Service type
- Energy only (ERIS)
- Study phase
- Executed
- Queue status
- Withdrawn
- Entered queue
- 13 October 2010
- Agreement signed
- 28 March 2014
- Proposed online date
- May 2022
- Withdrawn
- April 2025
Location
Marker shows the centre of Yolo County; the queue data does not give exact sites.
Power plants in California · Transmission lines in California
Other requests in Yolo County
- Conaway Hybrid Power PlantSolar + storage · 170 MW · in study
- South WillowSolar · 413 MW · withdrawn
- DunniganOnshore wind · 301 MW · withdrawn
- Berryessa Wind FarmOnshore wind · 158 MW · withdrawn
- King Flat Wind Farm 1Onshore wind · 152 MW · withdrawn
- King Flat Wind Farm 2Onshore wind · 102 MW · withdrawn
- Dunnigan HillsOnshore wind · 100 MW · withdrawn
- Wellhead Power WintersGas · 49.0 MW · withdrawn
- Wellhead Power Woodland CHPGas · 49.0 MW · withdrawn
- Zamora SolarSolar · 30.0 MW · withdrawn
- Woodland Battery ProjectBattery storage · 25.0 MW · withdrawn
- Plainfield SolarSolar · 20.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem