United States βΊ Grid βΊ Interconnection queues βΊ California
GAS Β· CAISOWellhead Power Winters
Wellhead Power Winters is a 49.0 MW gas request withdrawn in the CAISO interconnection queue, in Yolo County, California, connecting to PGAE.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2008 (completed)
- Withdrawn / abandonedNov 2008 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 351
- Grid region
- CAISO (California)
- Utility / transmission owner
- PGAE
- Connection point (POI)
- Tap Vaca-Rio Oso 115 kV line
- Location
- Yolo County, California
- Technology
- Gas: 49.0 MW
- Total requested
- 49.0 MW
- Study phase
- System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 25 April 2008
- Proposed online date
- July 2009
- Withdrawn
- November 2008
Location
Marker shows the centre of Yolo County; the queue data does not give exact sites.
Power plants in California Β· Transmission lines in California
Other requests in Yolo County
- Conaway Hybrid Power PlantSolar + storage Β· 170 MW Β· in study
- South WillowSolar Β· 413 MW Β· withdrawn
- DunniganOnshore wind Β· 301 MW Β· withdrawn
- Berryessa Wind FarmOnshore wind Β· 158 MW Β· withdrawn
- King Flat Wind Farm 1Onshore wind Β· 152 MW Β· withdrawn
- King Flat Wind Farm 2Onshore wind Β· 102 MW Β· withdrawn
- Dunnigan HillsOnshore wind Β· 100 MW Β· withdrawn
- Wellhead Power Woodland CHPGas Β· 49.0 MW Β· withdrawn
- Zamora SolarSolar Β· 30.0 MW Β· withdrawn
- Woodland Battery ProjectBattery storage Β· 25.0 MW Β· withdrawn
- Apparent First HybridSolar + storage Β· 24.1 MW Β· withdrawn
- Plainfield SolarSolar Β· 20.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem