United States β€Ί Grid β€Ί Interconnection queues β€Ί California

SOLAR Β· CAISO

South Willow

South Willow is a 413 MW solar request withdrawn in the CAISO interconnection queue, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2023 (completed)
  2. Withdrawn / abandonedDec 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
54802
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
RIO OSO 230 kV
Location
California
Technology
Solar: 413 MW
Total requested
413 MW
Service type
Energy only (ERIS)
Study phase
Caiso Cluster 15 Unvalidated
Queue status
Withdrawn
Entered queue
17 April 2023
Proposed online date
December 2030
Withdrawn
December 2024

Location

Marker shows the centre of County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem