United States β€Ί Grid β€Ί Interconnection queues β€Ί California

SOLAR Β· CAISO

Plainfield Solar

Plainfield Solar is a 20.0 MW solar request withdrawn in the CAISO interconnection queue, in Yolo County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2011 (completed)
  2. Withdrawn / abandonedJun 2011 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
742
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Line Tap to 69 KV - Plainfield
Location
Yolo County, California
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
31 March 2011
Proposed online date
March 2013
Withdrawn
June 2011

Location

Marker shows the centre of Yolo County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Yolo County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem