Zamora Solar

Zamora Solar is a 30.0 MW solar request withdrawn in the CAISO interconnection queue, in Yolo County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2011 (completed)
  2. Withdrawn / abandonedMar 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
780
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Woodland - Zamora - Rio Oso #2 115kV Bus
Location
Yolo County, California
Technology
Solar: 30.0 MW
Total requested
30.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
31 March 2011
Proposed online date
March 2013
Withdrawn
March 2012

Location

Marker shows the centre of Yolo County; the queue data does not give exact sites.