United States β€Ί Grid β€Ί Interconnection queues

OTHER Β· PJM

Other project AD1-086

Other project AD1-086 is a 23.9 MW other request withdrawn in the PJM interconnection queue, connecting to ComEd.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2017 (completed)
  2. Withdrawn / abandonedAug 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AD1-086
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ComEd
Connection point (POI)
E. Frankfort-Goodings Grove
Technology
Other: 23.9 MW
Total requested
23.9 MW
Service type
Energy only (ERIS)
Study phase
Available studies: System Impact Study, Facilities Study
Queue status
Withdrawn
Entered queue
15 September 2017
Proposed online date
June 2021
Withdrawn
August 2021

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem