πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Oklahoma

SOLAR Β· SPP

Solar project GEN-2021-SR3, Oklahoma County

Solar project GEN-2021-SR3, Oklahoma County is a 23.4 MW solar request withdrawn in the SPP interconnection queue, in Oklahoma County, Oklahoma.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2021 (completed)
  2. Withdrawn / abandonedSep 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. OperatingOct 2022 (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2021-SR3
Grid region
SPP (Southwest Power Pool)
Location
Oklahoma County, Oklahoma
Technology
Solar: 23.4 MW
Total requested
23.4 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
12 February 2021
Proposed online date
October 2022
Came online
October 2022
Withdrawn
September 2021

Location

Marker shows the centre of Oklahoma County; the queue data does not give exact sites.

Power plants in Oklahoma Β· Transmission lines in Oklahoma

Other requests in Oklahoma County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem