United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 340

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 340 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Moss Ridge Solar
Solar · Moss Ridge Solar 1
46.0 MWWithdrawn / abandoned St. Lawrence, NYNYISO Aug 2020
Upper Falls Solar
Solar + storage · Upper Falls Solar
46.0 MWWithdrawn / abandoned Wyoming, NYNYISO Sep 2024
Onshore wind project Z1-042, Mifflin County
Onshore wind
46.0 MWWithdrawn / abandoned Mifflin, PAPJM Aug 2013target 2015
Star GL Storage 2
Battery storage
45.8 MWWithdrawn / abandoned Sutter, CACAISO Apr 2018target 2021
Solar project J3770, Randolph County
Solar
45.8 MWWithdrawn / abandoned Randolph, ILMISO Apr 2024target 2027
NY Southold 50100 County Rd 48 Storage B
Battery storage · Bluewave Storage Origination LLC
45.7 MWWithdrawn / abandoned Suffolk, NYNYISO Sep 2022
Onshore wind project 420-B, San Juan County
Onshore wind · EDF Renewable Development, Inc
45.6 MWWithdrawn / abandoned San Juan, UTWest Mar 2012target 2014
Solar project 206, Suwannee County
Solar · Masked
45.4 MWWithdrawn / abandoned Suwannee, FLSoutheast Nov 2017target 2019
Battery Storage
Battery storage
45.3 MWWithdrawn / abandoned Litchfield, CTISO-NE Jun 2024target 2027
Gas project 508, Utah County
Gas · Jordan Cove Energy Project, L.P.
45.0 MWWithdrawn / abandoned Utah, UTWest Aug 2013target 2014
Solar project 48, Polk County
Solar
45.0 MWWithdrawn / abandoned Polk, FLSoutheast Nov 2018target 2020
Solar project J881, Jasper County
Solar
45.0 MWWithdrawn / abandoned Jasper, ILMISO Jun 2017target 2019
Battery storage project J1971, Dane County
Battery storage
45.0 MWWithdrawn / abandoned Dane, WIMISO Nov 2021target 2025
Cowboy Newt Solar
Solar · Belltown Power
45.0 MWWithdrawn / abandoned ERCOT Mar 2018target 2020
Battery storage project J2285, Polk County
Battery storage
45.0 MWWithdrawn / abandoned Polk, MNMISO Jul 2021target 2026
Solar project TCS-33, Bonneville County
Solar
45.0 MWWithdrawn / abandoned Bonneville, IDWest Jun 2019target 2021
Carrizo Solar Farm I
Solar
45.0 MWWithdrawn / abandoned San Luis Obispo, CACAISO Jul 2007target 2008
Solar project 13, Hillsborough County
Solar
45.0 MWWithdrawn / abandoned Hillsborough, FLSoutheast Apr 2017target 2018
Biomass Project
Other
45.0 MWWithdrawn / abandoned Hillsborough, NHISO-NE May 2007target 2010
Solar project J894, Woodruff County
Solar
45.0 MWWithdrawn / abandoned Woodruff, ARMISO Jun 2017target 2020
Centinela Solar Energy Expansion II - 45 MW Expansion
Solar
45.0 MWWithdrawn / abandoned Imperial, CACAISO Mar 2011target 2014
Solar project 941, Weber County
Solar
45.0 MWWithdrawn / abandoned Weber, UTWest Sep 2017target 2019
Ee Borrego II
Solar
45.0 MWWithdrawn / abandoned San Diego, CACAISO Mar 2011target 2015
McCommas Power Project
Other · McCommas Landfill Partners, LP
45.0 MWWithdrawn / abandoned ERCOT Jul 2005target 2050
Solar + storage project LGE-GIS-2022-008, Lee County
Solar + storage
45.0 MWWithdrawn / abandoned Lee, VASoutheast Sep 2022target 2024
Other project W2-004, Essex County
Other
45.0 MWWithdrawn / abandoned Essex, NJPJM May 2010target 2012
Sunshine 3
Solar
45.0 MWWithdrawn / abandoned Kern, CACAISO Mar 2011target 2014
Solar project J2146, Hopkins County
Solar
45.0 MWWithdrawn / abandoned Hopkins, KYMISO Nov 2021target 2024
Hydro project S124, Hancock County
Hydro
45.0 MWWithdrawn / abandoned Hancock, WVPJM Jul 2007target 2010
Solar project J3491, Posey County
Solar
45.0 MWWithdrawn / abandoned Posey, INMISO Apr 2024target 2028
Tehachapi Valley Solar I
Solar
45.0 MWWithdrawn / abandoned Kern, CACAISO Apr 2012target 2016
Solar + storage project AD1-050, Mecklenburg County
Solar + storage
45.0 MWWithdrawn / abandoned Mecklenburg, VAPJM Aug 2017target 2019
Nuclear project A54, Dauphin County
Nuclear
45.0 MWWithdrawn / abandoned Dauphin, PAPJM Feb 1999target 2002
Solar project AC1-210, Madison County
Solar
45.0 MWWithdrawn / abandoned Madison, OHPJM Oct 2016target 2018
Solar project 919799, Anderson County
Solar
45.0 MWWithdrawn / abandoned Anderson, SCSoutheast Sep 2023
Solar project AG2-368, Buckingham County
Solar
45.0 MWWithdrawn / abandoned Buckingham, VAPJM Mar 2021target 2025
Solar project 1143, Bonneville County
Solar
45.0 MWWithdrawn / abandoned Bonneville, IDWest Jun 2019target 2021
Onshore wind project H058, Stearns County
Onshore wind
45.0 MWWithdrawn / abandoned Stearns, MNMISO Jun 2008target 2011
Onshore wind project GEN-2006-001, Ellis County
Onshore wind
45.0 MWWithdrawn / abandoned Ellis, OKSPP Jan 2006target 2006
Tierra Del Sol Solar Farm
Solar
45.0 MWWithdrawn / abandoned San Diego, CACAISO Mar 2011target 2016
Solar project Q72, Pinal County
Solar
45.0 MWWithdrawn / abandoned Pinal, AZWest Sep 2009target 2012
Battery storage project J1877, Decatur County
Battery storage
45.0 MWWithdrawn / abandoned Decatur, INMISO Mar 2022target 2024
Onshore wind project 218-B, Iron County
Onshore wind
45.0 MWWithdrawn / abandoned Iron, UTWest May 2008target 2011
Solar project AF2-262, Luzerne County
Solar
45.0 MWWithdrawn / abandoned Luzerne, PAPJM Mar 2020target 2023
Solar project 2019-G5
Solar
45.0 MWWithdrawn / abandoned West Apr 2019target 2021
KPP - 45
Gas
45.0 MWWithdrawn / abandoned Kern, CACAISO Apr 2012target 2019
Solar project AE1-181, Luzerne County
Solar
45.0 MWWithdrawn / abandoned Luzerne, PAPJM Sep 2018target 2020
Battery storage project AH1-586, Sussex County
Battery storage · RWE Solar Development, LLC
45.0 MWWithdrawn / abandoned Sussex, DEPJM Jan 2025target 2024
Solar + storage project J2836, Livingston County
Solar + storage
45.0 MWWithdrawn / abandoned Livingston, KYMISO Sep 2022target 2025
Battery storage project J1862, Clinton County
Battery storage
45.0 MWWithdrawn / abandoned Clinton, MIMISO Aug 2021target 2024
Page 340 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)