United States βΊ Grid βΊ Interconnection queues βΊ Michigan
BATTERY STORAGE Β· MISOBattery storage project J1862, Clinton County
Battery storage project J1862, Clinton County is a 45.0 MW battery storage request withdrawn in the MISO interconnection queue, in Clinton County, Michigan, connecting to METC.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2021 (completed)
- Withdrawn / abandonedMar 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1862
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- METC
- Connection point (POI)
- Bingham West 138kV
- Location
- Clinton County, Michigan
- Technology
- Battery: 45.0 MW
- Total requested
- 45.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 3; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 16 August 2021
- Proposed online date
- September 2024
- Withdrawn
- March 2025
Location
Marker shows the centre of Clinton County; the queue data does not give exact sites.
Other requests in Clinton County
- Solar project J1553, Clinton CountySolar Β· 150 MW Β· agreement signed
- Onshore wind project J4195, Clinton CountyOnshore wind Β· 300 MW Β· in study
- Solar project J2674, Clinton CountySolar Β· 200 MW Β· withdrawn
- Solar project J1589, Clinton CountySolar Β· 150 MW Β· withdrawn
- Solar project J3203, Clinton CountySolar Β· 150 MW Β· withdrawn
- Solar project J2710, Clinton CountySolar Β· 100 MW Β· withdrawn
- Onshore wind project J070, Clinton CountyOnshore wind Β· 49.2 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem