πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

SOLAR Β· MISO

Solar project J3203, Clinton County

Solar project J3203, Clinton County is a 150 MW solar request withdrawn in the MISO interconnection queue, in Clinton County, Michigan, connecting to METC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedMar 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3203
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
Bingham - Lookng GL J 138kV
Location
Clinton County, Michigan
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
15 September 2022
Proposed online date
July 2026
Withdrawn
March 2023

Location

Marker shows the centre of Clinton County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Clinton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem