United States βΊ Grid βΊ Interconnection queues βΊ Utah
SOLAR Β· WESTSolar project 941, Weber County
Solar project 941, Weber County is a 45.0 MW solar request withdrawn in the West interconnection queue, in Weber County, Utah, connecting to PacifiCorp.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2017 (completed)
- Withdrawn / abandonedMar 2022 (project stopped here)
- ConsentedJan 2019 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 941
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- PacifiCorp
- Connection point (POI)
- Marquart-Little Mountain transmission line
- Location
- Weber County, Utah
- Technology
- Solar: 45.0 MW
- Total requested
- 45.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA Executed 1/18/19, suspended 1/24/19, terminated 3/30/22
- Queue status
- Withdrawn
- Entered queue
- 5 September 2017
- Agreement signed
- 18 January 2019
- Proposed online date
- December 2019
- Withdrawn
- March 2022
Location
Marker shows the centre of Weber County; the queue data does not give exact sites.
Other requests in Weber County
- Battery storage project C3-171, Weber CountyBattery storage Β· 200 MW Β· in study
- Battery storage project 725, Weber CountyBattery storage Β· 0.3 MW Β· built
- Gas project 307, Weber CountyGas Β· 400 MW Β· withdrawn
- Gas project 264, Weber CountyGas Β· 380 MW Β· withdrawn
- Gas project 244, Weber CountyGas Β· 380 MW Β· withdrawn
- Battery storage project C3-170, Weber CountyBattery storage Β· 200 MW Β· withdrawn
- Gas project 424, Weber CountyGas Β· 175 MW Β· withdrawn
- Battery storage project C2-66, Weber CountyBattery storage Β· 150 MW Β· withdrawn
- Solar project 1000, Weber CountySolar Β· 120 MW Β· withdrawn
- Solar project 993, Weber CountySolar Β· 74.9 MW Β· withdrawn
- Solar project 293-A, Weber CountySolar Β· 30.0 MW Β· withdrawn
- Solar project 317, Weber CountySolar Β· 19.9 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem