United States βΊ Grid βΊ Interconnection queues βΊ Virginia
SOLAR + STORAGE Β· SOUTHEASTSolar + storage project LGE-GIS-2022-008, Lee County
Solar + storage project LGE-GIS-2022-008, Lee County is a 45.0 MW solar + storage request withdrawn in the Southeast interconnection queue, in Lee County, Virginia, connecting to Louisville Gas & Electric and Kentucky Utilities Energy.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2022 (completed)
- Withdrawn / abandonedSep 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- LGE-GIS-2022-008
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Louisville Gas & Electric and Kentucky Utilities Energy
- Connection point (POI)
- Pocket North Substation 161 kV bus
- Location
- Lee County, Virginia
- Technology
- Solar: 45.0 MW Β· Battery
- Total requested
- 45.0 MW
- Service type
- NRIS and ERIS
- Queue status
- Withdrawn
- Entered queue
- 7 September 2022
- Proposed online date
- September 2024
- Withdrawn
- September 2023
Location
Marker shows the centre of Lee County; the queue data does not give exact sites.
Other requests in Lee County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem