πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

SOLAR Β· WEST

Solar project 2019-G5

Solar project 2019-G5 is a 45.0 MW solar request withdrawn in the West interconnection queue, connecting to WAPA Rocky Mountain Region.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2019 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
2019-G5
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA Rocky Mountain Region
Connection point (POI)
Sidney Solar 115-kV
Technology
Solar: 45.0 MW
Total requested
45.0 MW
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
18 April 2019
Proposed online date
January 2021

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem