United States › Grid › Interconnection queues › California

BATTERY STORAGE · CAISO

Star GL Storage 2

Star GL Storage 2 is a 45.8 MW battery storage request withdrawn in the CAISO interconnection queue, in Sutter County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2018 (completed)
  2. Withdrawn / abandonedApr 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1464
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Greenleaf #1 Tap 115 kV
Location
Sutter County, California
Technology
Battery: 45.8 MW
Total requested
45.8 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
16 April 2018
Proposed online date
December 2021
Withdrawn
April 2019

Location

Marker shows the centre of Sutter County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Sutter County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem