BATTERY STORAGE · CAISO

Tierra Buena Energy Center

Tierra Buena Energy Center is a 74.4 MW battery storage request withdrawn in the CAISO interconnection queue, in Sutter County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2018 (completed)
  2. Withdrawn / abandonedApr 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1466
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Pease 60kV
Location
Sutter County, California
Technology
Battery: 74.4 MW
Total requested
74.4 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
16 April 2018
Proposed online date
September 2021
Withdrawn
April 2019

Location

Marker shows the centre of Sutter County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Sutter County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem