United States β€Ί Grid β€Ί Interconnection queues β€Ί California

SOLAR Β· CAISO

Ee Borrego II

Ee Borrego II is a 45.0 MW solar request withdrawn in the CAISO interconnection queue, in San Diego County, California, connecting to SDGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2011 (completed)
  2. Withdrawn / abandonedMar 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
699
Grid region
CAISO (California)
Utility / transmission owner
SDGE
Connection point (POI)
Borrego Substation 69kV bus
Location
San Diego County, California
Technology
Solar: 45.0 MW
Total requested
45.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
31 March 2011
Proposed online date
June 2015
Withdrawn
March 2012

Location

Marker shows the centre of San Diego County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in San Diego County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem