Battery storage interconnection queue in the USA — page 33

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,226417.8 GW
Active in queue417.8 GW2,226 requests
Agreement signed76.1 GW459 requests
Withdrawn3,516554.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,226 requests · page 33 of 45
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project GEN-2019-002, Mayes County
Battery storage
100 MWAgreement signed Mayes, OKSPP Nov 2018target 2027
Battery storage project GEN-2022-154, Cleveland County
Battery storage
100 MWIn study Cleveland, OKSPP Feb 2023target 2027
Palmvalley Storage
Battery storage
100 MWPaused / redesign Hidalgo, TXERCOT Sep 2022target 2025
Battery storage project AG2-332, Elkhart County
Battery storage · Amberjack Solar LLC
100 MWIn study Elkhart, INPJM Feb 2025target 2024
Battery storage project T2-041, Multnomah County
Battery storage
100 MWIn study Multnomah, ORWest Sep 2025target 2027
Battery storage project GEN-2018-026, Canadian County
Battery storage
100 MWAgreement signed Canadian, OKSPP May 2018target 2026
Battery storage project AJ1-019, Southampton County
Battery storage
100 MWIn study Southampton, VAPJM Jun 2023target 2028
Battery storage project GI-TC-2024-18, Montezuma County
Battery storage
100 MWIn study Montezuma, COWest May 2024target 2027
Battery storage project 12-054, Clackamas County
Battery storage
100 MWPaused / redesign Clackamas, ORWest Dec 2012target 2014
Battery storage project AI2-005, Fluvanna County
Battery storage
100 MWIn study Fluvanna, VAPJM Oct 2022target 2028
Battery storage project IA-PNM-2019-18, Bernalillo County
Battery storage
100 MWPaused / redesign Bernalillo, NMWest Apr 2019target 2022
Harwood Power
Battery storage
100 MWAgreement signed King George, VAPJM Oct 2019target 2029
Battery storage project 145, Whatcom County
Battery storage
100 MWIn study Whatcom, WAWest Apr 2024target 2027
PSE Richardson TX Storage
Battery storage · PureSky Development Inc.
100 MWIn study Hidalgo, TXERCOT Dec 2022target 2027
Battery storage project J3007, Mason County
Battery storage
100 MWIn study Mason, MIMISO Aug 2022target 2025
Battery storage project AH2-126, Jefferson County
Battery storage
100 MWIn study Jefferson, OHPJM Feb 2022target 2026
Battery storage project Company 210, Clark County
Battery storage
100 MWPaused / redesign Clark, NVWest Sep 2021target 2024
Battery storage project C2-204, Yakima County
Battery storage
100 MWIn study Yakima, WAWest May 2022target 2024
Battery storage project 86, Whatcom County
Battery storage
100 MWAgreement signed Whatcom, WAWest Jul 2020target 2030
Battery storage project J4140, Ouachita Parish County
Battery storage
100 MWIn study Ouachita Parish, LAMISO Sep 2025target 2030
Battery storage project AH2-121, Mchenry County
Battery storage
100 MWIn study Mchenry, ILPJM Feb 2022target 2028
South Bronx Energy Storage
Battery storage · Prologis Energy LLC
100 MWIn study Bronx, NYNYISO Sep 2024target 2030
Battery storage project AJ1-003, Mecklenburg County
Battery storage
100 MWIn study Mecklenburg, VAPJM Apr 2023target 2028
Battery storage project AG2-343, Fountain County
Battery storage · Dolphin Solar LLC
100 MWIn study Fountain, INPJM Feb 2025target 2024
Battery storage project J3158, Cerro Gordo County
Battery storage
100 MWIn study Cerro Gordo, IAMISO Sep 2022target 2027
Battery storage project 327, Citrus County
Battery storage · Duke Energy Florida, LLC
100 MWUnder construction Citrus, FLSoutheast May 2023target 2027
Battery storage project AH2-034, Prince William County
Battery storage
100 MWIn study Prince William, VAPJM Nov 2021target 2028
Battery storage project AJ1-002, Rockingham County
Battery storage
100 MWIn study Rockingham, VAPJM Apr 2023target 2028
Battery storage project GEN-2022-156, Creek County
Battery storage
100 MWIn study Creek, OKSPP Feb 2023target 2027
Battery storage project GEN-2018-027, Tulsa County
Battery storage
100 MWAgreement signed Tulsa, OKSPP May 2018target 2028
Battery storage project AH2-330, City Of Chesapeake County
Battery storage
100 MWIn study City Of Chesapeake, VAPJM Mar 2022target 2027
Marlboro Storage
Battery storage · Origis Development LLC
100 MWIn study Ulster, NYNYISO Oct 2024target 2028
Battery storage project GEN-2021-041, Canadian County
Battery storage
100 MWAgreement signed Canadian, OKSPP Apr 2021target 2027
Battery storage project AJ1-016, Cambria County
Battery storage
100 MWIn study Cambria, PAPJM Jun 2023target 2028
Battery storage project Company 221, Clark County
Battery storage
100 MWPaused / redesign Clark, NVWest Mar 2022target 2029
Eastwater Energy Storage
Battery storage · GCI Eastwater, LLC
100 MWIn study Monroe, NYNYISO Aug 2024target 2027
Battery storage project J3172, Dakota County
Battery storage
100 MWIn study Dakota, MNMISO Sep 2022target 2026
Battery storage project J2064, Jackson County
Battery storage
100 MWIn study Jackson, MIMISO Nov 2021target 2024
Horseblock Energy Storage
Battery storage · ACE DevCo NC, LLC
100 MWIn study Suffolk, NYNYISO Aug 2024target 2028
Zenobe Burns LLC
Battery storage · Zenobe Americas Inc.
100 MWIn study Allegany, NYNYISO Sep 2024target 2028
Battery storage project GEN-2021-039, Douglas County
Battery storage
100 MWIn study Douglas, NESPP Apr 2021target 2030
Galvanic BESS
Battery storage · CED Development Inc
100 MWIn study Kinney, TXERCOT Feb 2021target 2027
Battery storage project J2124, Champaign County
Battery storage
100 MWIn study Champaign, ILMISO Aug 2021target 2022
Battery storage project Company 222, Clark County
Battery storage
100 MWPaused / redesign Clark, NVWest Mar 2022target 2029
Golden Fields Solar
Battery storage
100 MWAgreement signed Kern, CACAISO Apr 2015target 2026
Battery storage project J1845, Calhoun County
Battery storage
100 MWIn study Calhoun, MIMISO Dec 2020target 2025
Battery storage project 146, Skagit County
Battery storage
100 MWIn study Skagit, WAWest Apr 2024target 2027
Battery storage project AH2-035, Prince William County
Battery storage
100 MWIn study Prince William, VAPJM Nov 2021target 2028
Battery storage project AG2-300, Frederick County
Battery storage · Meadow Brook Storage, LLC
100 MWIn study Frederick, VAPJM Feb 2025target 2023
Battery storage project 3RSC-2023-02, Pueblo County
Battery storage
100 MWIn study Pueblo, COWest May 2023target 2025
Page 33 of 45

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)