BATTERY STORAGE · MISOBattery storage project J3172, Dakota County
Battery storage project J3172, Dakota County is a 100 MW battery storage request in interconnection study in the MISO interconnection queue, in Dakota County, Minnesota.
Queue statusIn planning
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3172
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- GRE-NININGR7 115 kV
- Location
- Dakota County, Minnesota
- Technology
- Battery: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 14 September 2022
- Proposed online date
- June 2026
Location
Marker shows the centre of Dakota County; the queue data does not give exact sites.
Other requests in Dakota County
- Battery storage project J2716, Dakota CountyBattery storage · 300 MW · in study
- Battery storage project J4065, Dakota CountyBattery storage · 200 MW · in study
- Battery storage project J3543, Dakota CountyBattery storage · 150 MW · in study
- Solar project J2027, Dakota CountySolar · 150 MW · in study
- Hydro project J1826, Dakota CountyHydro · 4.0 MW · in study
- Hydro project J3219, Dakota CountyHydro · 3.0 MW · in study
- Gas project J399, Dakota CountyGas · 232 MW · built
- Coal project G020, Dakota CountyCoal · 147 MW · built
- Gas project G259, Dakota CountyGas · 1,100 MW · withdrawn
- Gas project G223, Dakota CountyGas · 750 MW · withdrawn
- Gas project G168, Dakota CountyGas · 700 MW · withdrawn
- Gas project G271, Dakota CountyGas · 670 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem