Gas project J399, Dakota County is a 232 MW gas request built and operating in the MISO interconnection queue, in Dakota County, Minnesota.
Request details
- Queue ID
- J399
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Black Dog 115 kV substation
- Location
- Dakota County, Minnesota
- Technology
- Gas: 232 MW
- Total requested
- 232 MW
- Study phase
- DPP - SIS
- Queue status
- Operational
- Entered queue
- 15 October 2014
- Agreement signed
- 1 September 2017
- Proposed online date
- February 2018
- Came online
- February 2018
Location
Marker shows the centre of Dakota County; the queue data does not give exact sites.
Other requests in Dakota County
- Battery storage project J2716, Dakota CountyBattery storage · 300 MW · in study
- Battery storage project J4065, Dakota CountyBattery storage · 200 MW · in study
- Battery storage project J3543, Dakota CountyBattery storage · 150 MW · in study
- Solar project J2027, Dakota CountySolar · 150 MW · in study
- Battery storage project J3172, Dakota CountyBattery storage · 100 MW · in study
- Hydro project J1826, Dakota CountyHydro · 4.0 MW · in study
- Hydro project J3219, Dakota CountyHydro · 3.0 MW · in study
- Coal project G020, Dakota CountyCoal · 147 MW · built
- Gas project G259, Dakota CountyGas · 1,100 MW · withdrawn
- Gas project G223, Dakota CountyGas · 750 MW · withdrawn
- Gas project G168, Dakota CountyGas · 700 MW · withdrawn
- Gas project G271, Dakota CountyGas · 670 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem