United States › Grid › Interconnection queues › New York

BATTERY STORAGE · NYISO

South Bronx Energy Storage

South Bronx Energy Storage is a 100 MW battery storage request in interconnection study in the NYISO interconnection queue, in Bronx County, New York, connecting to NYPA.

Queue statusIn planning
  1. PlanningQueued Sep 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
C24-284
Grid region
NYISO (New York)
Utility / transmission owner
NYPA
Developer
Prologis Energy LLC
Connection point (POI)
Hell Gate 138 kV Substation
Location
Bronx County, New York
Technology
Battery: 100 MW
Total requested
100 MW
Queue status
Active
Entered queue
25 September 2024
Proposed online date
December 2030

Location

Marker shows the centre of Bronx County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Bronx County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem