BATTERY STORAGE · NYISOBlue Spruce Storage
Blue Spruce Storage is a 300 MW battery storage request in interconnection study in the NYISO interconnection queue, in Bronx County, New York, connecting to ConEd.
Queue statusIn planning
- PlanningQueued Aug 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Aug 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- C24-005
- Grid region
- NYISO (New York)
- Utility / transmission owner
- ConEd
- Developer
- Blue Spruce Storage LLC
- Connection point (POI)
- Mott Haven 138KV Bus
- Location
- Bronx County, New York
- Technology
- Battery: 300 MW
- Total requested
- 300 MW
- Queue status
- Active
- Entered queue
- 1 August 2024
- Proposed online date
- August 2028
Location
Marker shows the centre of Bronx County; the queue data does not give exact sites.
Other requests in Bronx County
- Palladium StorageBattery storage · 140 MW · in study
- Port Morris Energy StorageBattery storage · 130 MW · in study
- South Bronx Energy StorageBattery storage · 100 MW · in study
- Hell Gate Energy StorageBattery storage · 90.0 MW · in study
- NY Wind - Mott Haven CSRWind + storage · 1,400 MW · withdrawn
- NY Wind - Mott HavenOffshore wind · 1,272 MW · withdrawn
- Oak Point YardGas · 500 MW · withdrawn
- Tremont BESSBattery storage · 300 MW · withdrawn
- Bronx Shores Energy StorageBattery storage · 300 MW · withdrawn
- Palladium StorageBattery storage · 255 MW · withdrawn
- Blue Spruce StorageBattery storage · 245 MW · withdrawn
- Clover Leaf Hollers AveGas · 193 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem