United States › Grid › Interconnection queues › New York
BATTERY STORAGE · NYISOEastwater Energy Storage
Eastwater Energy Storage is a 100 MW battery storage request in interconnection study in the NYISO interconnection queue, in Monroe County, New York, connecting to NM-NG.
Queue statusIn planning
- PlanningQueued Aug 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- C24-072
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NM-NG
- Developer
- GCI Eastwater, LLC
- Connection point (POI)
- Station 82 - Station 121 Line 23 115kV
- Location
- Monroe County, New York
- Technology
- Battery: 100 MW
- Total requested
- 100 MW
- Queue status
- Active
- Entered queue
- 2 August 2024
- Proposed online date
- June 2027
Location
Marker shows the centre of Monroe County; the queue data does not give exact sites.
Other requests in Monroe County
- High Acres LandfillOther · 6.4 MW · built
- Brown's Race IIIHydro · 2.0 MW · built
- Brown's Race IIIHydro · 2.0 MW · built
- Russell StationGas · 325 MW · withdrawn
- Jasper StorageBattery storage · 300 MW · withdrawn
- Russell Station IICoal · 300 MW · withdrawn
- Lighthouse Energy StorageBattery storage · 250 MW · withdrawn
- Krenzer SolarSolar · 150 MW · withdrawn
- KrenzerSolar · 150 MW · withdrawn
- Janes Rd StorageBattery storage · 100 MW · withdrawn
- Janes Road Energy StorageBattery storage · 100 MW · withdrawn
- Hamlin Wind FarmOnshore wind · 80.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem