HYDRO · NYISOBrown's Race III
Brown's Race III is a 2.0 MW hydro request built and operating in the NYISO interconnection queue, in Monroe County, New York, connecting to RG&E.
Request details
- Queue ID
- 340
- Grid region
- NYISO (New York)
- Utility / transmission owner
- RG&E
- Developer
- RG&E
- Connection point (POI)
- Station 6 34.5 kV
- Location
- Monroe County, New York
- Technology
- Hydro: 2.0 MW
- Total requested
- 2.0 MW
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 2 September 2009
- Came online
- January 2012
Location
Marker shows the centre of Monroe County; the queue data does not give exact sites.
Other requests in Monroe County
- Eastwater Energy StorageBattery storage · 100 MW · in study
- High Acres LandfillOther · 6.4 MW · built
- Brown's Race IIIHydro · 2.0 MW · built
- Russell StationGas · 325 MW · withdrawn
- Jasper StorageBattery storage · 300 MW · withdrawn
- Russell Station IICoal · 300 MW · withdrawn
- Lighthouse Energy StorageBattery storage · 250 MW · withdrawn
- Krenzer SolarSolar · 150 MW · withdrawn
- KrenzerSolar · 150 MW · withdrawn
- Janes Rd StorageBattery storage · 100 MW · withdrawn
- Janes Road Energy StorageBattery storage · 100 MW · withdrawn
- Hamlin Wind FarmOnshore wind · 80.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem