United States › Grid › Interconnection queues › New York
BATTERY STORAGE · NYISOJanes Rd Storage
Janes Rd Storage is a 100 MW battery storage request withdrawn in the NYISO interconnection queue, in Monroe County, New York, connecting to RG&E.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2024 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1664
- Grid region
- NYISO (New York)
- Utility / transmission owner
- RG&E
- Developer
- MN8 Energy Operating Company
- Connection point (POI)
- Station 69 to Station 7 115 kV line tap
- Location
- Monroe County, New York
- Technology
- Battery: 100 MW
- Total requested
- 100 MW
- Queue status
- Withdrawn
- Entered queue
- 10 January 2024
Location
Marker shows the centre of Monroe County; the queue data does not give exact sites.
Other requests in Monroe County
- Eastwater Energy StorageBattery storage · 100 MW · in study
- High Acres LandfillOther · 6.4 MW · built
- Brown's Race IIIHydro · 2.0 MW · built
- Brown's Race IIIHydro · 2.0 MW · built
- Russell StationGas · 325 MW · withdrawn
- Jasper StorageBattery storage · 300 MW · withdrawn
- Russell Station IICoal · 300 MW · withdrawn
- Lighthouse Energy StorageBattery storage · 250 MW · withdrawn
- Krenzer SolarSolar · 150 MW · withdrawn
- KrenzerSolar · 150 MW · withdrawn
- Janes Road Energy StorageBattery storage · 100 MW · withdrawn
- Hamlin Wind FarmOnshore wind · 80.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem