BATTERY STORAGE Β· NYISOJasper Storage
Jasper Storage is a 300 MW battery storage request withdrawn in the NYISO interconnection queue, in Monroe County, New York, connecting to RG&E.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2022 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1457
- Grid region
- NYISO (New York)
- Utility / transmission owner
- RG&E
- Developer
- Hanwha Q CELLS USA Corp.
- Connection point (POI)
- Henrietta (S255) 345 kV Substation
- Location
- Monroe County, New York
- Technology
- Battery: 300 MW
- Total requested
- 300 MW
- Queue status
- Withdrawn
- Entered queue
- 1 November 2022
Location
Marker shows the centre of Monroe County; the queue data does not give exact sites.
Other requests in Monroe County
- Eastwater Energy StorageBattery storage Β· 100 MW Β· in study
- High Acres LandfillOther Β· 6.4 MW Β· built
- Brown's Race IIIHydro Β· 2.0 MW Β· built
- Brown's Race IIIHydro Β· 2.0 MW Β· built
- Russell StationGas Β· 325 MW Β· withdrawn
- Russell Station IICoal Β· 300 MW Β· withdrawn
- Lighthouse Energy StorageBattery storage Β· 250 MW Β· withdrawn
- Krenzer SolarSolar Β· 150 MW Β· withdrawn
- KrenzerSolar Β· 150 MW Β· withdrawn
- Janes Rd StorageBattery storage Β· 100 MW Β· withdrawn
- Janes Road Energy StorageBattery storage Β· 100 MW Β· withdrawn
- Hamlin Wind FarmOnshore wind Β· 80.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem