United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in MISO (Midcontinent) — page 33

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3,261621.9 GW
Active in queue350.1 GW1,646 requests
Agreement signed28.1 GW187 requests
Withdrawn3,261621.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3,261 requests · page 33 of 66
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project G904, Rolette County
Onshore wind
150 MWWithdrawn / abandoned Rolette, NDMISO Nov 2007target 2010
Solar project J3610, Tyler County
Solar
150 MWWithdrawn / abandoned Tyler, TXMISO Apr 2024target 2028
Solar project J2328, Lonoke County
Solar
150 MWWithdrawn / abandoned Lonoke, ARMISO Sep 2022target 2027
Onshore wind project J975, Cass County
Onshore wind
150 MWWithdrawn / abandoned Cass, NDMISO Mar 2018target 2023
Solar project J2488, Bay County
Solar
150 MWWithdrawn / abandoned Bay, MIMISO Sep 2022target 2025
Solar project J1111, Jackson County
Solar
150 MWWithdrawn / abandoned Jackson, ILMISO Mar 2018target 2021
Solar project J2108, Johnson County
Solar
150 MWWithdrawn / abandoned Johnson, IAMISO Aug 2021target 2024
Solar project J910, Hinds County
Solar
150 MWWithdrawn / abandoned Hinds, MSMISO Jun 2017target 2020
Solar + storage project J2962, Hamilton County
Solar + storage
150 MWWithdrawn / abandoned Hamilton, ILMISO Sep 2022target 2026
Solar project J2291, Polk County
Solar
150 MWWithdrawn / abandoned Polk, MNMISO Sep 2021target 2025
Solar + storage project J2857, Tunica County
Solar + storage
150 MWWithdrawn / abandoned Tunica, MSMISO Sep 2022target 2024
Solar project J1108, Douglas County
Solar
150 MWWithdrawn / abandoned Douglas, MNMISO Mar 2018target 2021
Solar project J3333, Washtenaw County
Solar
150 MWWithdrawn / abandoned Washtenaw, MIMISO Apr 2024target 2028
Solar project J3921, Jasper County
Solar
150 MWWithdrawn / abandoned Jasper, IAMISO Mar 2025target 2027
Onshore wind project G339, Dickey County
Onshore wind
150 MWWithdrawn / abandoned Dickey, NDMISO May 2003target 2003
Solar project J3037, Union County
Solar
150 MWWithdrawn / abandoned Union, ARMISO Sep 2022target 2027
Onshore wind project MPC02900, Barnes County
Onshore wind
150 MWWithdrawn / abandoned Barnes, NDMISO Jul 2016target 2018
Onshore wind project J273, Dewitt County
Onshore wind
150 MWWithdrawn / abandoned Dewitt, ILMISO Mar 2013
Onshore wind project J257, Newton County
Onshore wind
150 MWWithdrawn / abandoned Newton, INMISO Oct 2012target 2018
Onshore wind project MPC02400, Oliver County
Onshore wind
150 MWWithdrawn / abandoned Oliver, NDMISO Jan 2009target 2011
Solar project J1416, Worth County
Solar
149 MWWithdrawn / abandoned Worth, IAMISO Apr 2019target 2022
Onshore wind project R67, Clay County
Onshore wind
149 MWWithdrawn / abandoned Clay, IAMISO May 2009target 2010
Onshore wind project G622, Dickey County
Onshore wind
149 MWWithdrawn / abandoned Dickey, NDMISO Apr 2006target 2007
Solar project J3677, Daviess County
Solar
148 MWWithdrawn / abandoned Daviess, INMISO Apr 2024target 2027
Solar project J3201, Walthall County
Solar
148 MWWithdrawn / abandoned Walthall, MSMISO Sep 2022target 2026
Solar project J647, Muskegon County
Solar
147 MWWithdrawn / abandoned Muskegon, MIMISO Jun 2016target 2021
Onshore wind project J1713, Macon County
Onshore wind
147 MWWithdrawn / abandoned Macon, ILMISO Jun 2020target 2022
Onshore wind project J921, Ionia County
Onshore wind
147 MWWithdrawn / abandoned Ionia, MIMISO Jun 2017target 2019
Solar project J1539, West Baton Rouge Parish, La County
Solar
146 MWWithdrawn / abandoned West Baton Rouge Parish, La, LAMISO Jun 2020target 2023
Gas project J810, Audubon County
Gas
146 MWWithdrawn / abandoned Audubon, IAMISO Jun 2017target 2023
Solar project J3103, Fountain County
Solar
145 MWWithdrawn / abandoned Fountain, INMISO Jun 2022target 2026
Onshore wind project J2323, Webster County
Onshore wind
145 MWWithdrawn / abandoned Webster, IAMISO Sep 2022target 2027
Battery storage project J3329, Sullivan County
Battery storage
145 MWWithdrawn / abandoned Sullivan, INMISO Apr 2024target 2028
Onshore wind project J1120, Jefferson County
Onshore wind
145 MWWithdrawn / abandoned Jefferson, TXMISO Mar 2018target 2021
Solar project J1878, Decatur County
Solar
145 MWWithdrawn / abandoned Decatur, INMISO Aug 2021target 2024
Solar project J3422, Lawrence County
Solar
145 MWWithdrawn / abandoned Lawrence, ARMISO Mar 2024target 2028
Onshore wind project J1176, Cerro Gordo County
Onshore wind
145 MWWithdrawn / abandoned Cerro Gordo, IAMISO Mar 2018target 2021
Onshore wind project J3091, Logan County
Onshore wind
145 MWWithdrawn / abandoned Logan, NDMISO Sep 2022target 2026
Solar + storage project J2615, Warren County
Solar + storage
145 MWWithdrawn / abandoned Warren, INMISO Sep 2022target 2026
Solar project J1715, Decatur County
Solar
145 MWWithdrawn / abandoned Decatur, INMISO Jun 2020target 2023
Onshore wind project J474, Dewitt County
Onshore wind
144 MWWithdrawn / abandoned Dewitt, ILMISO Sep 2015target 2017
Solar project J2093, Crittenden County
Solar
144 MWWithdrawn / abandoned Crittenden, ARMISO Dec 2021target 2024
Onshore wind project J3405, St. Louis County
Onshore wind
144 MWWithdrawn / abandoned St. Louis, MNMISO Apr 2024target 2028
Onshore wind project G599, Adams County
Onshore wind
144 MWWithdrawn / abandoned Adams, ILMISO Feb 2006target 2014
Onshore wind project G598, Adams County
Onshore wind
144 MWWithdrawn / abandoned Adams, ILMISO Feb 2006target 2006
Onshore wind project J2919, Montgomery County
Onshore wind
143 MWWithdrawn / abandoned Montgomery, INMISO Sep 2022target 2027
Battery storage project J2531, Union Parish County
Battery storage
140 MWWithdrawn / abandoned Union Parish, LAMISO Sep 2022target 2026
Onshore wind project MPC01800, Burleigh County
Onshore wind
140 MWWithdrawn / abandoned Burleigh, NDMISO Dec 2008target 2011
Battery storage project J2527, Allen Parish County
Battery storage
140 MWWithdrawn / abandoned Allen Parish, LAMISO Sep 2022target 2025
Solar + storage project J3071, St. Francis County
Solar + storage
140 MWWithdrawn / abandoned St. Francis, ARMISO Sep 2022target 2024
Page 33 of 66

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)