ONSHORE WIND Β· MISO

Onshore wind project J975, Cass County

Onshore wind project J975, Cass County is a 150 MW onshore wind request withdrawn in the MISO interconnection queue, in Cass County, North Dakota, connecting to OTTER TAIL POWER COMPANY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2018 (completed)
  2. Withdrawn / abandonedJul 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J975
Grid region
MISO (Midcontinent)
Utility / transmission owner
OTTER TAIL POWER COMPANY
Connection point (POI)
Buffalo 115kV Substation
Location
Cass County, North Dakota
Technology
Wind: 150 MW
Total requested
150 MW
Service type
Energy only (ERIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
12 March 2018
Proposed online date
October 2023
Withdrawn
July 2021

Location

Marker shows the centre of Cass County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Cass County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem