ONSHORE WIND Β· MISO

Onshore wind project G599, Adams County

Onshore wind project G599, Adams County is a 144 MW onshore wind request withdrawn in the MISO interconnection queue, in Adams County, Illinois.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2006 (completed)
  2. Withdrawn / abandonedJan 2012 (project stopped here)
  3. ConsentedJan 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G599
Grid region
MISO (Midcontinent)
Connection point (POI)
S. Quincy - Meredosia 120 kV
Location
Adams County, Illinois
Technology
Wind: 144 MW
Total requested
144 MW
Study phase
Network Upgrade
Queue status
Withdrawn
Entered queue
15 February 2006
Agreement signed
4 January 2012
Proposed online date
January 2014
Withdrawn
January 2012

Location

Marker shows the centre of Adams County; the queue data does not give exact sites.

Power plants in Illinois Β· Transmission lines in Illinois

Other requests in Adams County