ONSHORE WIND Β· PJM

Onshore wind project Z2-086, Adams County

Onshore wind project Z2-086, Adams County is a 200 MW onshore wind request withdrawn in the PJM interconnection queue, in Adams County, Illinois, connecting to ComEd.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2014 (completed)
  2. Withdrawn / abandonedMay 2014 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Z2-086
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ComEd
Location
Adams County, Illinois
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Energy only (ERIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
29 April 2014
Withdrawn
May 2014

Location

Marker shows the centre of Adams County; the queue data does not give exact sites.

Power plants in Illinois Β· Transmission lines in Illinois

Other requests in Adams County